Acquisition
Specialist
The Acquisition
Specialist is the subject matter expert on the State acquisition process and provides
oversight to OSI projects during all phases of the Acquisition Life Cycle.
The Acquisition Specialist works in the
OSI Procurement Center
and is assigned to a project during the Project Initiation phase. The
Acquisition Specialist provides guidance and direction on the development and approval
of the Request For Proposal and associated documents (e.g. Information Technology
Procurement Plan, GC 19130 Justification Form, Evaluation and Selection Report,
etc.) from planning through execution of the contract. The Acquisition Specialist
acts the liaison between the OSI project and the Department of General Services
to ensure full compliance with all acquisition-related requirements and OSI Best
Practices. The Acquisition Specialist continues to work with the project as-needed
after the contract is executed to provide guidance on contract management issues,
such as vendor performance, dispute resolution, and contract close-out requirements.
|
|
Acquisition Team
The Acquisition Team is responsible for managing and/or
coordinating all procurement activities. The team works
closely with the OSI Procurement Center during Planning and
Contracting phases of the Acquisition Life Cycle. The team
is led by the Procurement Manager under the guidance of the
Acquisition Specialist. In addition to these two
participants, the team is typically comprised of subject
matter experts as identified by the project.
|
|
Administrative Manager
The Administrative
Manager directs the administrative staff, coordinates tools and services training,
ensures that the administrative staff adhere to processes and policies, leads the
cost management effort including: sponsoring cost budgeting and tracking activities,
facilitating communication on fiscal status, and ensuring the project cost tool
and supporting documentation is maintained. The Administrative Manager also provides
reports, recommendations, and status on the project budget and expenditures, e.g.,
planned vs. actual reports, initiates corrective action, and re-planning activities.
|
|
Administrative Staff Support Services
The Administrative
Staff Services Support is responsible for supporting the Administrative Manager
by providing staff services-related activities; acting as the help desk liaison
between the Project Office and external stakeholders; serving as personnel liaison
and training coordinator. The Administrative Staff
Support Services also supports
the Administrative Manager by providing support for acquiring new or additional
facility space and/or infrastructure resources, providing asset management oversight,
making preparation for contract arrival and staff orientation, providing clerical/secretarial
support, maintaining conference room calendars and distribution lists, and managing
incoming/outgoing mail.
|
|
Application Support Manager
The Application
Support Manager is responsible for overseeing and coordinating the change request
process for installed software and for ensuring the change requests adhere to specified
quality and configuration standards. They manage application design sessions and
walkthroughs, application change management processes and acceptance testing of
application changes. They monitor contractor performance of application support
and ensure that contractor maintains quality control.
|
|
Configuration Manager
The Configuration
Manager is responsible for supporting the Technical Manager by administering the
Configuration Management process, coordinating the control of all non-product related
configuration items, working with the contractors to manage and coordinate the product
related configuration items, assisting the System Engineer in maintaining the requirements
database, and conducting configuration audits. The Configuration Management also
leads work with project stakeholders, in particular, the Change and Release Management
Group for approval to release programs and configuration modifications into the
production environment.
|
|
Contract Manager
The Contract
Manager is responsible for managing and tracking the Prime Contractor and consulting
contracts for the project. This includes negotiating amendments, reviewing work
authorizations and invoices, and ensuring that all contractual terms and deliverables
are met.
For projects
that have many project consultants, a separate contract manager may be needed specifically
for overseeing the consultants. This may also be the case when the Prime Contract
has a large number of deliverables and contract terms which need to be managed and
tracked, so a separate manager for consultants would allow the Prime Contract Manager
to focus their efforts.
|
|
Customer Support Manager
The Customer
Support Manager is responsible for overseeing the M&O Contractor service efforts,
and assisting the customer with special requests or problems. The Customer Support
Manager provides customer perspective and problem prioritization, monitors contractor
service levels and metrics.
|
|
Department of Finance (DOF) Representative
The DOF representative
is responsible for reviewing and approving project-funding documents such as BCPs,
and SPRs.
|
|
D epartment of General Services (DGS)
Procurement Official
The DGS Procurement
Official coordinates and oversees the procurement process, ensures the evaluation
is conducted in accordance with applicable state laws regulations and policies and
in accordance with the project’s documented evaluation procedures, serves as the
single point of contact to bidders and stakeholders for questions regarding the
procurement and evaluation process, maintains the Master Copy of all proposals and
the official procurement files, provides guidance to the Evaluation Team, coordinates
the issuance of any addenda to the RFP and any responses to bidder questions, coordinates
responses to any protest, and reviews the Evaluation and Selection Report.
|
|
Department of Technology Services (DTS)
Data
Center
Representative
The DTS Data
Center Representative acts as the liaison between the Project Office and the DTS
in defining required services, assisting the project in determining the feasibility
of services, cost estimates, planning, and other technical assistance to aid the
project in making informed data center decisions.
|
|
End User
The end
user is the person or organization that will use the
project's end product.
|
|
E xecutive Steering Committee
The Executive
Steering Committee acts as the Project stakeholders group, ensuring that the deliverables
and functionality of the project are achieved as defined in the project initiation
documents and subsequent project management plans. This committee provides high-level
project direction, receives project status updates, and addresses and resolves issues,
risks, or change requests.
|
|
Financial Analyst
The Financial
Analyst is responsible for supporting the Administrative Manager by managing and
tracking project budget/costs, coordinating/preparing budgetary documents, e.g.,
Special Project Reports and OSI Budget Change Proposals, reviewing budget/contract
expenditures, and collecting and reporting financial metrics. This includes reconciling
the accounting and Work Breakdown Structure cost management processes and developing
financial management policies and procedures. The Financial Analyst also provides
support in project solicitations, evaluations, and award processes - assisting in
the evaluation of the cost and administrative sections of the proposals based on
the criteria in the Evaluation Plan.
|
|
Implementation Manager
The Implementation
Manager (IM) will be responsible for the implementation portion of the project.
The IM will provide implementation management leadership through planning, organizing,
coordinating, and monitoring implementation activities. In addition, the IM will
be responsible for effectively managing all information technology resources assigned
by the project manager, including implementation strategy, organizational change
management, production support, IT training/knowledge transfer, defect/problem tracking,
and Maintenance & Operation. The IM will coordinate SOWs and interface directly
with contractors to ensure technical obligations satisfy all objectives and expectations.
|
|
Independent Project Oversight Consultant
(IPOC)
The IPOC works under the direction of the Project Sponsor to
provide independent project management oversight in
accordance with the Office of the State Chief Information
Officer (OCIO) Information Technology Project Oversight
Framework:
http://www.cio.ca.gov/Government/IT_Policy/pdf/IT_OvrsghtFrmwrkR2-25-04s.pdf
|
|
Independent Verification and Validation
(IV&V)
The IV&V
representatives work under the direction of the Project Sponsor to provide IV&V
against the project. The IV&V team will provide independent, technical review
and verification of project deliverables, as well as independent testing and auditing
of project deliverables against requirements, with a special emphasis placed on
deliverable quality assurance and information security control reviews.
|
|
Legal Counsel
The legal
representative provides legal opinions upon request in areas of the RFP or RFO and
Service Request content, contract amendments, work authorizations, contracting questions,
conflicts of interest, discovery issues, communication documents, industry trends,
and general contracting issues.
|
|
Operations Manager
The Operations
Manager is responsible for coordinating and overseeing the operations of the new
system. This includes overseeing problem resolution and administration and operations
activities. They monitor prime contractor management of operations and resolution
of operations support problems.
|
|
Operation
Support Team
The Operation Support Team includes all individuals
that are responsible for daily operations of the system
to ensure that the system operates as intended once
implemented.
|
|
Procurement Manager
The Procurement
Manager oversees and manages the generation of the RFP or RFO and other solicitation
documents. Other areas of the project office may be assigned responsibility for
specific sections, but the Procurement Manager is responsible for integrating all
the pieces and ensuring consistency and continuity throughout the entire procurement
process and conforming to procurement standards, rules, and regulations. This includes
managing the RFP or RFO development, preparing and maintaining procurement schedule,
coordinating contract negotiations and managing evaluation of proposals or offers
and selection of vendor.
|
|
Project Director
The Project
Director is responsible for planning, directing and overseeing the project, and
ensuring that deliverables and functionality are achieved as defined in the Project
Charter, funding documentation and subsequent project plans. The Project Director
is also responsible for the management of all resources assigned to the project,
serves as the primary liaison between the project and the Project Sponsor and Executive
Committee, and escalates decisions and issues as needed. The Project Director coordinates
project related issues with other efforts, reviews and resolves project issues not
resolved at lower levels, and directs the project management functions. The Project
Director acts as the principle interface to the contractors.
|
|
Project Librarian
The Project
Librarian is responsible for supporting the Administrative Manager by acting as
the librarian lead, assisting with contract deliverable tracking, and assisting
with administrative services support activities.
|
|
Project Manager
The Project
Manager is accountable to the Project Director for all the project office management
related activities. The Project Manager plans, guides, and oversees the day-to-day
internal activities that support the Project Office, and assists in the development
of the master project schedule and all other project work plans. The Project Manager
is accountable for the development, maintenance, and adherence to the Project Office
infrastructure and supporting methodologies (e.g. processes, procedures, standards,
and templates) that are in compliance with OSI Best Practices and policies.
|
|
Project Scheduler
The Project
Scheduler is responsible for coordinating and managing inputs to the project plan.
This includes tracking progress against project schedule, merging and identifying
dependencies and risks between the project schedule, tracking progress on prime
contractor's schedule and counties' schedules.
|
|
Project Sponsor
The Project
Sponsor has overall authority for the project. The Project Sponsor provides vision
and direction for the project, provides policy leadership, assists in removing barriers
and supports change management initiatives, participates in the Executive Steering
Committee, and provides support to the Executive Steering Committee as needed.
|
|
Project Stakeholder
External resources
included in the staff planning estimates should be described here. If the resource
is only providing review or response to questions, it is not necessary to describe
the organization in this section.
A full description
of all external stakeholders should be in the Governance Plan or Communication Plan,
so this section should only highlight those organizations that are lending staff
or significant time to the project to support project activities.
Indicate the
type of support the organization is providing and whether the resources are full
or part-time and if they are on-site or off-site. Also describe whom the externals
“report” to in the project and/or the type of relationship, peer, advisor/counsel,
etc.
|
|
Project Team
The project team member(s) is responsible for creating
the requirements traceability matrix document based upon
the project contract, system and software
specifications, detailed design specifications, creating
and managing the project test case document, providing
necessary test result input for the creation of the
testing summary report. A project team member may be
assigned the responsibility for constructing the test
summary report and provide a completed version to the
Project Manager. The project team member(s) is
responsible for creating and managing the test log
document, testing accordingly, and creating the
operational support documentation.
|
|
Quality Manager
The Quality
Manager is responsible for overseeing and ensuring both product and process quality
for the project office as well as for the Prime Contractor. The Quality Manager
provides insight into the project and contractor methods of doing business by reviewing
process and product activities for adherence to standards and plans.
|
|
Risk Manager
The Risk Manager
is responsible for managing and tracking risks and risk mitigation/contingencies
on the project. The Risk Manager also monitors prime contractor risk management
efforts to ensure they do not adversely impact the project. The Risk Manager manages
and tracks potential and active risks, maintain the risk management tool and documentation
information, leads risk identification sessions for the project, monitors prime
contractor risk management efforts, and participates in division-level risk management
activities for risks that cross project boundaries or are beyond the project’s control.
|
|
Solution Architect
The primary
role of the Solution Architect is to translate what is required to run the business
into actual design specifications and models that can be supported and fulfilled
by components within the Technology Architecture.
|
|
System Engineer
The System
Engineer is a co-leadership position with the Technical Manager in overseeing the
technical aspects of the project and is a direct support to the Technical Manager.
The System Engineer provides industry best practices and disciplines that will be
applied and tailored to suit the processes and culture of the state technical environment.
The System
Engineer will support the Technical Manager primarily in providing technical leadership
towards the development and tracking of the system business requirements and interfaces,
assisting with technical analyses, and ensuring the final system meets all stated
requirements. The System Engineer will also be responsible for the following: tracking
and managing the requirements for the new system and any changes to the requirements,
providing exposure to project stakeholders on new technologies and processes relevant
to the project, providing training of the evaluation team, and holding technical
simulations of the project as needed.
|
|
Technical Manager
The Technical
Manager is responsible for the day-to-day activities of state and vendor technical
staff who are engaged in the technical management aspects of the project. The technical
manager (a state manager for the project) and system engineer (a consultant on the
project) co-lead in the technical disciplines of the project, unlike the Project
Director and Project Manager who will focus on the overall project management of
the project.
One of the
key roles of the Technical Manager is to partner with other IT managers to acquire
appropriate technical assistance for such areas as enterprise architecture, database,
software development, security, testing, configuration management, change management,
release management, and other technical areas of the new system. The Technical Manager,
along with the system engineer, will provide leadership and support to technical
staff that are augmented to the project throughout the project life cycle.
The Technical
Manager will also provide technical support to the Project Director, Project Manager,
and other managers in the Project Office to establish and execute technical policies,
processes, and procedures.
|
|
Test Manager
The Test Manager is responsible for coordinating the testing
of the Prime Contractor's system. The Manager works with the
Quality Management staff to design test cases and data that
will best represent "real-life" scenarios for the system.
The Test Manager is also responsible for coordinating
interface tests with other organizations (county, state,
federal), as needed. They plan, monitor, and evaluate prime
contractor test plans, problem reporting and resolution
process.
|
| |